Home Gujarat SVPIA sets national record in runway work, 3.5 kms long runway completed...

SVPIA sets national record in runway work, 3.5 kms long runway completed in just 75 days

385
0
SHARE

(G.N.S) Dt. 14

Ahmedabad

Sardar Vallabhbhai Patel International Airport (SVPIA), managed by the Adani Group,has completed the recarpeting work on its 3.5-kilometre-long runway ina record time of 75 days. This duration is an all-timebest among brownfield runwaysin India.

Ahmedabad’s SVPIA is the busiest airport in Gujarat with over 200 flights every day in the pre-covid time. The challenge of recarpeting the runway without impacting the operations of scheduled flights was tackled by Adani Airport Holdings Ltd (AAHL)by using only nine hours of NOTAM (Notice to Airmen) daily.During the 75 days it took to complete the project, SVPIA kept the runway open daily for 160 flights on an averageduring the remaining 15 hours of the day.

The quantum of asphalt laid for the recarpeting was equivalent to a 200 km stretch of road, while the concrete used for the runway drainage system was sufficient to build a 40-storied structure.

The project was earlier planned for 200 working days starting from 10 November 2021. However, in keeping with the brand’s continued endeavour to improve operational efficiency and reduce inconvenience to passengers, the Adani Group had reset the target to 90 days by increasing the resources.Subsequently, SVPIA’s project team completed the work in just 75 days. The project entailedthe support of 1 Mn safe manhours and 600 individuals featuring staff and workmen along with over 200 sophisticatedpieces of equipment.

LEAVE A REPLY

Please enter your comment!
Please enter your name here